SpaceX Wins Conditional FCC Approval for Up to 1 Million AI Data Center Satellites

The US Federal Communications Commission authorized SpaceX on November 25, 2026, to deploy up to one million satellites for its Starmind orbital AI computing network, subject to conditions governing communications, deployment, and disposal.
The FCC’s order grants the application in part and defers it in part. It provides regulatory permission for the constellation, not confirmation that a million satellite data center has been built or that its engineering and economics are proven.
SpaceX filed its application on January 30. The FCC’s February 4 acceptance for filing opened the proposal to comments; it was not an approval.
What the Authorization Permits
The decision covers specified orbital shells approximately 500 to 1,002 kilometers above Earth. Deployment above 600 kilometers remains conditional on a further final debris mitigation submission.
Authorized direct radio links are for backup and emergency telemetry, tracking and command. They must not cause harmful interference and receive no protection from other operators. SpaceX must stop operations causing documented harmful interference.
Ordinary network connectivity would principally use optical links between satellites, including connections through Starlink. Required ground station permissions and federal coordination remain applicable.
The FCC did not approve SpaceX’s proposed alternative disposal arrangements. Satellites not destined for atmospheric reentry would require a further authorization modification before deployment.
How SpaceX Plans to Operate the Network
According to SpaceX’s Starmind program page , its first generation AI1 spacecraft would carry modular computing equipment, with a deployed wingspan of 75 meters and an average computing payload electrical power of 175 kilowatts. These are design specifications, not measured flight performance.
SpaceX proposes solar power, radiators, and fluid cooling systems. Optical connections would link the computing satellites with one another and Starlink.
Deployment Targets and Remaining Tests
SpaceX’s securities filing describes plans for a factory in Bastrop, Texas, targeting production and deployment of thousands of AI satellites starting as soon as late 2027. That remains a company target.
The FCC requires one operational satellite by November 25, 2033, followed by 100,000 in 2035, 500,000 in 2038, and the full authorized constellation in 2040.
SpaceX has not demonstrated an operational Starmind AI data center. Cooling performance, reliable computing, network capacity, and deployment costs remain key tests before the authorized scale becomes an operating system.